By providing your contact information to Anna Sillery, your personal information will be processed in accordance with Anna Sillery's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Anna Sillery in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Anna Sillery at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.
Thank you for your message. I will be in touch with you shortly.
Explore Our Properties
Weathered silver cedar shingles, white casement windows and a shaded glass porch door above a brick foundation, with oakleaf hydrangea in morning light.

John Nesbitt Loop: Wrightsville Beach Bridge Construction Plans

October 22, 2026

For most of a year, the John Nesbitt Loop won't work as a loop. The first phase of NCDOT's three-bridge replacement closes West Salisbury Street over Lees Cut. That bridge is one of three state bridges built into the Loop's circuit, and it closes before any official pedestrian detour has been published. The Town of Wrightsville Beach and the New Hanover Community Endowment are treating that gap as the start of the Loop's next version. The money and design work now underway are aimed at keeping people walking during construction and at a wider Loop afterward.

A sidewalk built from leftovers

The Loop started small. According to a Wrightsville Beach Magazine history, John Nesbitt and his crew began building a sidewalk so residents could walk safely to the post office. They used undedicated funds and concrete left over from other jobs. Nesbitt became the town's building inspector in 1976 and its public works director in 1979, and he retired in 1999, the StarNews reported. The paper began using the trail's full name in 2008 at the request of his widow, Ann Nesbitt.

That sidewalk is now a heavily used facility. The town's October 2025 request for qualifications describes the Loop as a 2.45-mile sidewalk trail "used daily by thousands of residents and visitors weekly." It is a 5-foot sidewalk with a parallel goat path along much of its length. The same document calls the sidewalk narrow for the number of people walking or running side by side and pushing single or double strollers. It adds that residents have asked in recent planning input for a wider Loop.

The route starts at the town complex. It runs down Causeway Drive, turns onto North Lumina Avenue, comes back along West Salisbury Street, and returns to the start on Causeway. Along the way it passes Wrightsville Beach Park next to the Parks and Recreation offices, the Wrightsville Beach Museum of History in its historic beach cottage on the Salisbury side, and the Wrightsville Beach Arboretum's benches where Causeway Drive meets Salisbury Street. The town's RFQ states the key fact plainly: the Loop includes all three NCDOT bridges scheduled for replacement.

The first break comes at Lees Cut

Lees Cut is the short bridge on Salisbury Street, and it goes first. NCDOT awarded the Phase 1 contract to Balfour Beatty for $8.67 million. Waterline relocation on Pelican Drive and the West Salisbury Street shoulder was expected to begin in October and take four to eight weeks. NCDOT said the bridge will fully close once that utility work is done, and that the public will be told when an official closure date is set.

The town's planning gives a tighter window. At the Bridge Replacement Committee's August 31 meeting, GFT Engineering's Chad Kimes said the Lees Cut closure was scheduled for October to November 2026 and expected to last nine to 12 months. Port City Daily reported that the closure runs from Lookout Harbour to the eastern entrance of Pelican Drive. The new bridge will be built just north of the existing one, and the old span will be removed while the new one goes up.

WECT reported that at the committee's October 5 meeting, members discussed restricting access to the Loop once Lees Cut construction begins. The town said it would share details on when the Loop will be blocked once dates are available.

During the Lees Cut phase Status as of mid-October 2026
Full closure of West Salisbury over Lees Cut Follows waterline work, no official date announced
Expected length of closure 9 to 12 months, per August 31 committee minutes
Restricted Loop access Confirmed in committee discussion, timing to come from the town
Causeway Drive bridge Stays open to vehicles and pedestrians
Causeway Drive multi-use path Reported to remain open
Two lanes each way on Causeway Committed for the whole project
Official pedestrian route around Lees Cut Not yet published

The Causeway side is the part that stays. Port City Daily reported that during Phase 1, two lanes in each direction remain open on Causeway Drive along with its multi-use path, and the Causeway bridge stays open to pedestrians. The Arboretum, Wrightsville Beach Park, and the walk out to North Lumina all sit on that side. The stretch past Lookout Harbour toward Pelican Drive is the one in question.

The money is aimed at the construction window

The town is working on keeping a path open during construction, not just after it. At the committee's June 15 meeting, the town manager said the town wanted to widen the Loop and "establish a multiuse path while the bridges are being constructed." He said preliminary design was underway and that the town and Board of Aldermen had budgeted funds for the work. WilmingtonBiz had reported in April that the town had hired a contractor to design the Loop improvements.

Outside money arrived on September 29. The New Hanover Community Endowment announced a $1.5 million grant to add to the town's investment in the first phase of improvements to the John T. Nesbitt Loop. The Endowment said the project "will help maintain a walking route during the N.C. Department of Transportation's three-year bridge replacement project." It will also support planning and design for a wider, fully accessible Loop. The Wrightsville Beach grant was one of seven totaling $15.8 million. Another, $3.5 million, went toward Carolina Beach's planned Coastal Park and Event Stage near the Boardwalk.

The expansion area in the RFQ shows where the town plans to widen the Loop:

  • Causeway Drive from Salisbury Street to Coral Drive
  • A multi-use path connection from Causeway Drive through Wrightsville Beach Park
  • That connection continuing to the existing multi-use path at the tennis and pickleball courts, which links to West Salisbury Street

Each of those pieces is meant to connect to the bicycle and pedestrian features NCDOT is building into the replacement bridges. The town hasn't yet said publicly which firm is building the expansion or when construction starts.

What the new bridges add to the circuit

The 5-foot sidewalk is the baseline. WECT reported that each new span will have a multi-use path 10 to 12 feet wide and a 6-foot dedicated bike lane. Port City Daily reported that on the new Causeway bridge the path will be 12 feet wide, with concrete parapet walls separating it from traffic and bike lanes on every bridge. On the bridge sections, that roughly doubles the Loop's current walking width and puts a wall between walkers and the road.

Getting there takes several steps. Once Lees Cut reopens, the Salisbury bridge over Banks Channel closes and work starts on the new bridge beside the existing Causeway span, according to the August 31 minutes. Port City Daily reported that during the Salisbury long-bridge phase, West Salisbury will close from Lookout Harbor to North Lumina Avenue, while street parking on West Salisbury stays available. NCDOT's target for finishing all three bridges moved up from 2032 to spring 2030. NCDOT Division 3 Highway Engineer Trevor Carroll called that date "our target."

Kyle Hanlin, executive director of the Wrightsville Beach Chamber of Commerce, summed up the tradeoff at a July meeting reported by WWAY:

"I think the juice is worth the squeeze. The disruption is going to be tough, but at the same time, again with communication and people realizing that Wrightsville Beach is going to have an even enhanced traffic problem with these bridges down, getting that word out there the right way I think is going to help mitigate these next 4 to 6 years."

The drawbridge changes on the same schedule

Anyone who walks or drives off the island will feel a second change that starts with the Lees Cut closure. At the August 31 meeting, chair Neal Andrew said NCDOT had a verbal agreement with the Coast Guard for the Heide Trask Drawbridge to open only at the top of the hour, starting when Lees Cut closes. The committee's October 5 agenda listed written approval as still pending.

The formal version is a Coast Guard proposed rule in the Federal Register, Docket No. USCG-2026-0758. Under the current schedule, the bridge opens on signal for commercial vessels at all times and only on the hour for pleasure vessels between 7 a.m. and 7 p.m. The proposal would extend the hourly limit to commercial vessels too, so from 7 a.m. to 7 p.m. daily the bridge would open only on the hour for all vessels. That schedule would run from 12:01 a.m. on November 1, 2026, through 11:59 p.m. on June 30, 2030. The comment period closed September 28. Carroll told reporters that pleasure boats would pass at the top-of-the-hour opening, and commercial towing or dredging vessels would call for 30 minutes' notice.

The dates on the calendar now

The Loop still runs its usual fall routine until the closure date is announced:

  1. Monday, October 26, 8 a.m. to 1 p.m. The Wrightsville Beach Farmers' Market sets up at Wrightsville Beach Park, 321 Causeway Drive, on the side of the Loop that stays open.
  2. Friday, October 30, 6:45 to 9 p.m. Movies in the Park returns to Wrightsville Beach Park.
  3. Sunday, November 1. The proposed start date for the on-the-hour drawbridge schedule, if the rule is finalized as written.
  4. Monday, November 9, 10 a.m. The next Bridge Replacement Committee meeting at the Public Safety Building conference room, 3 Bob Sawyer Drive.

The committee has said it isn't the official source of project information and only passes along what it is given. It points residents to NCDOT's website and the town's own pages. The town's Bridge Replacement Project page is where the Lees Cut closure date and the Loop access details are expected to be posted first.

If the bridge work has you thinking about how the island will work for you over the next few years, whether that's your daily walk, a property on Harbor Island, or a home closer to the Causeway side, Anna Sillery is glad to talk it through calmly. Schedule a consultation, and we'll go over the timeline as it stands and what it means for your plans.